Sprints
Tracker can help you utilize the Scrum workflow approach. With this approach, your work is split into sprints, that is, development iterations of a certain duration. In the beginning of each iteration, the issues are evaluated and planned for the upcoming sprint.
Sprints are enabled by default on boards with a backlog and sprints. If you want to use sprints on a Basic board, enable a backlog on it.
Planning a sprint
Step 1. Evaluate the effort required to resolve the issues
Evaluate the effort for the backlog issues. The effort is measured in Story Points that determine the relative complexity of the project's issues. Each team decides internally how to define the effort needed to complete their issues. You can specify the estimated effort on the issue page in the Story Points field.
Use Planning Poker on the issue board to assess the complexity of issues within your team.
Step 2. Create a new sprint
When you create a board, you'll see your first sprint is already set up in the Backlog tab. If you have not planned it yet, proceed to the next step. If your first sprint is already completed and you want to create a new one:
-
In the Backlog tab, click + Create sprint to the right of the board.
-
Enter a name for the sprint, its duration, and start and end time. To start the sprint right away, leave the Start sprint option enabled.
-
Click Create sprint.
Step 3. Add issues to the sprint
There are several ways to add an issue to a sprint:
-
On the Backlog tab, drag an issue from the Backlog column to the sprint's column.
-
In the backlog or on the board, select the issue card, then click
→ Add to sprint and select the sprint you need. -
On the issue page, enter the board name or ID in the Boards field of the left panel and select a sprint in the Sprint field under Agile.
-
To quickly add multiple issues, use bulk edits: click → Select in an issue card on the board, then click other issues you want to add to the sprint. Once you select all issues, click Add to sprint in the bottom panel of the board and select the one you need.
By default, you can't add issues to a completed sprint. To do this, first enable the sprint display. To learn more, see View completed sprints.
Editing a sprint
To edit a sprint:
-
Open the Backlog tab. To the right of the sprint header, click
→ Edit. -
In the window that opens, you can rename the sprint, change its duration and start and end time, as well as enable the Start sprint option.
-
To save your changes, click Edit sprint.
Changing sprint status
When you've planned all your sprint issues and the start date arrives, click Start next to the sprint in the board's Backlog tab.
Once you complete your work on the sprint, click Complete next to it. If the sprint has any incomplete issues, you will be prompted to leave them in the current sprint, return them to the backlog, or move them to a new sprint that can be created immediately. As soon as all the issues are completed, the sprint will appear under Finished sprints.
View completed sprints
By default, completed sprints and their associated issues are hidden from the board. To view and manage completed sprints:
-
In the upper-right corner of the Backlog tab, click
Finished sprints. -
Hover over the sprint and click
ShowThe sprint will appear on the board next to active sprints.
-
To hide a completed sprint, click
Hide next to its name.